Project Timeline
Project phases are planned to occur during the following time periods:
1.0 Strategic Analysis
09.02.05 - 11.29.05
2.0 Visual Design
11.07.05 - 02.21.05
3.0 Build
12.30.05-04.14.06
4.0 Quality Assurance
03.21.06 - 04.26.06
5.0 Initial Launch - Stage 1
04.27.06
6.0 Conversion/Build and Launch - Stage 2
05.01.06 - 08.30.07